There are
a lot of interesting
scope change management techniques that can be
easily applied to your project. Here are three that will keep you out of
trouble.
Make Sure Only the Sponsor Approves Changes
A typical problem on a project is that the team does not
understand the roles of the sponsor, client and end users in the area of
change management. In general, the project sponsor is the person who is
funding the project. If the client were embodied in one person, it would
be the project sponsor. The people that the project team tends to work with most
often are users. These are the people that use the solution that
the project is building. The end users are the ones that will generally
make requests for changes to deliverables. However, no matter how
important a change is to a user, they cannot approve scope
changes. The sponsor (or their
designee) must give the approval. If the change is important enough the
sponsor will approve it, along with the appropriate budget and
duration changes. If the change is not important enough, it will not be
approved.
Saying 'Yes' to Change Requests
May not Show Good Client Focus
The project manager and project team sometimes think that
they are being client-focused by accepting scope change while still
trying to deliver the project within the original commitments. However,
if the project is delivered late or over budget, it is usually not good
enough to point out all the additional work that was included because of
this 'client focus'.
The sponsor is the primary client representative.
Allowing the sponsor (or their designee) to make scope change decisions
shows good client focus. If the project team or project manager approves
scope changes, he is not showing good client focus from the sponsor's
perspective.
An
Engaged Sponsor Will Often Say 'No' to Scope Change Requests
One of the neat things about enforcing the discipline of
having the sponsor approve scope change requests is that, unless the
change is very important, the sponsor will often say 'no'. The sponsor
is usually someone high in the organization. He normally doesn't want to
hear about requests for small changes. He wants the original project
fulfilled within the original commitments for cost, effort and duration.
Even though it may be hard for the project manager to say 'no', the
project sponsor usually doesn't have any problem saying 'no' to the
people in sponsor's own organization.