A lire sur: Tenstep
The first major step in building a schedule (sometimes
called a Project
Plan) is to create a
Work Breakdown Structure (WBS). This is a way
to identify to work that
is required to build the deliverables of the
project. The WBS allows
you to break the large project down into small
enough steps that the work
can be understood. The process for building the WBS is as follows
1. Identify the large “chunks of work” of the project
First determine the large chunks of work that must be
completed for the entire project to be completed. When you start, it
does not matter how you define the large chunks of work.
For instance, a traditional breakdown might be "planning / analysis
/ build / implement", which lays out the project
in a high-level timeline. The breakdown could also be by major deliverable
such as "permits, pool, fence, landscaping". You can break
down the work into whatever structure makes sense for your project.
2. Evaluate each lower element of the WBS
Check each component of the WBS to see if it meets
the following two criteria.
-
Do you (or someone on your team) understand the detailed work required to complete this work component? The detailed work components on the WBS will ultimately be moved to the schedule. You don’t want to have activities on your schedule that no one on your team fully understands.
-
Do a quick estimate of the work. Are the effort hours required to complete the work less than your estimating threshold? A rule of thumb is 80 hours or less, but this could be higher or lower based on the size of the project. If you don't understand the work, the chances are it will be larger than your estimating threshold as well.
If you understand the detailed work required to
complete the component and if the estimated level of effort is
smaller than the estimating threshold you do not need to break the
component down further.
3. Continue to break down each component as needed
Work components that require more effort than the
estimating threshold, or work components that you do not fully
understand should be broken down further into smaller pieces of work.
As you break the
work down, you are ultimately going to create activities that are
required to complete the deliverables. This is referred to as an
"activity based WBS". The
detailed activities from the WBS are what get carried forward to the
schedule.
This process of breaking the work components into a
lower level set of components should continue until all of the work
components are represented as granular as necessary to ensure that
no activities have estimated effort larger than the estimating
threshold, and that you understand the work. This takes you to
levels 3, 4, 5 etc. Rarely would you need to break the work down
greater than five levels.
Planning Components
There
is one exception to this process. If your
project is large
and long, it is likely that you may not know enough to be
able to break
all of the work down to a discreet level. Work that
takes place a
long way in the future may have to be left at a higher
level. These are
known as planning components. In that case, you can leave the work
components at
the higher level until you get closer to execution
(three months),
at which time you will know enough to be able to
break the work
down at a more granular level.
When
you are done with the process above, you will
understand the
work at the lowest levels of the WBS and the work will be
smaller than
your estimating thresholds. At that point the WBS is
completed.
Aucun commentaire:
Enregistrer un commentaire