At the completion of a major project milestone or phase,
the team should take a short pause to make sure the project is on track
and ready to proceed. This is a
gate
review and it includes taking a look behind to make sure all the
things you have completed all the things you should have.
The backward look includes the following.
-
Deliverable approvals. You should make sure that all of the deliverables that need approval have, in fact, been approved. Sometimes this final approval may even take place at the phase gate review meeting.
-
Budget and schedule review. The project budget should be reviewed to validate where you are at within your total budget estimate. Likewise you should look at your schedule to see if you are on schedule and take some corrective actions if necessary.
-
Review project issues. You should validate that all outstanding issues have been resolved or that there is a plan in place to resolve them
-
Review project risks. This is a good time for a risk control meeting. You should validate that your prior risks are being successfully managed or you need to revise your risk plans. You should also look for any new risks to your project.
Think
about the purpose of a gate. You open the gate, step through and move
forward. Similarly the most important part of a gate review is the
forward look. You need to be sure you are ready to move forward on the
project. The forward look includes the following.
-
Validate schedule and budget estimates. You should re-estimate the project cost and final schedule to make sure your current estimates for final spending and deadline are still valid.
-
Validate the Business Case. This is a time to check that the original Business Case is still valid. The gate review is a good opportunity to cancel a project that no longer makes sense.
-
Check that resources are available. In many projects, the types of resources and skills changes from phase to phase. This is an opportunity to validate you still have the resources required to complete the remainder of the project.
-
Validate your sponsorship. It is possible that the interest and commitment of the sponsor has waned since the project started. The sponsor may have changed. Use this time to validate the priority of the project with the sponsor and cancel the project if the sponsor is no longer committed.
Once
you have validated that all of the prior work is complete and
correct, plus you have validated the readiness to proceed, you
should obtain a formal approval to move to the next phase. In other
words, the phase “gate” is now open to enter and pass through.