A lire sur: Method123
Everyone can recognize and appreciate that a
scope change
request must be invoked for large changes to the project.
However, you may encounter resistance to formal scope change management
for small change requests. The sponsor and other project team members may
consider this to be unnecessary overhead for such small decisions.
They might be right. There are three alternate techniques
to employ that may help with small changes. None of these
options implies that you are not managing and tracking scope changes.
These are just additional techniques to use that may be more appropriate
for managing small scope changes.
-
Batching. It is not always practical to get the sponsor to approve all small scope change requests each time one is requested. The project team usually does not have day-to-day access to the sponsor and it is hard to get the sponsor’s attention for these small requests. It is a better use of time to batch the small changes up into a bundle. This means that you keep track of the small scope changes, their business value and their impact on the project. Then, when they hit a certain threshold, you take them all to the sponsor for approval. For example, instead of visiting the sponsor ten times for small scope changes, you batch the small changes together and see the sponsor one time.
-
Discretion. It may make sense for the project manager and a tactical customer manager to be given discretion to approve small scope change requests under some threshold of effort hours and cost. This authority must be explicitly delegated by the sponsor. This discretion assumes that the project is on or ahead of schedule, and that the changes do not make the project exceed the agreed-upon cost or duration. If the project is in any risk of not meeting its cost or duration commitments, this discretion should not be used – even for a one-hour change request. In this case, all changes should go through a normal scope change process to receive corresponding budget and schedule relief for any changes.
-
Scope Change Contingency Budget. Your organization may recognize that a certain level of scope change is inevitable and you may be allowed to allocate a percentage of the total project budget to account for small changes. For example, you may have a 5% contingency added to your budget for scope change. If your total project budget was $500,000, your scope change contingency budget would be $25,000 for small scope changes. The customer must rationalize the budget to make sure all important scope changes can be accommodated. If the customer uses the budget up early on small scope changes, there will be nothing left for later change requests. This budget is used for change requests under a certain dollar or hour threshold. Larger requests can still be made but they would go through normal scope change management and be evaluated by the sponsor.
Aucun commentaire:
Enregistrer un commentaire