A lire sur: Tenstep
This series of five emails describes the five most common project
management mistakes.
The
schedule is a vital tool to
ensure that the project manager and project team know what they need to do to
complete the project. If you have a poor schedule, or you don't update your
schedule, you are never quite sure how you are progressing
against your estimated deadline. If
possible start with a template. But even if you have a great
schedule to start you need to keep it up-to-date.
Mistake #3: Not Keeping
Schedule Up-to-Date
Many project managers create an initial schedule
but then don't do a good job of updating the schedule during the project. There are
trouble signs that the schedule is not
being updated.
-
The project manager cannot tell exactly what work is remaining to complete the project.
-
The project manager is unsure whether they will complete the project on-time.
-
The project manager does not know what the critical path of activities is.
-
Team members are not sure what they need to work on next (or even what they should be working on now).
It is a problem when the project manager does not really understand the progress made to date and how much
work is remaining. When this happens, the project team is not utilized
efficiently on the most critical activities.
There are a couple other
common scheduling problems.
-
Infrequent updates. Sometimes the project manager updates the schedule at lengthy intervals. For instance, updating the schedule every two months on a six-month project. This is not often enough to keep control of the schedule. The schedule should be updated every week or two.
-
Managing by percent complete. All activities should have a due date. As you monitor the work, keep focused on whether the work will be completed by the due date. It is not very valuable to know that an activity is 70% completed. It is more valuable to know if the due date will be hit.
-
Assigning activities that are too long. If you assign a team member an activity that is due by the end of the week, you know if the work is on-track when the week is over. However, if you assign someone an activity that does not need to be completed for eight weeks, you have a long time to go before you know if the work is really on schedule. Keep the due dates within a reasonable timeframe.
It is not easy to catch up a schedule once the project is started.
Typically, by the time you realize you need to update the schedule, your project
is already in trouble. Updating the schedule at that point only shows how much
trouble you are in. The much better approach is to keep the project up-to-date,
and ensure that it contains all of work necessary to complete the project.
Aucun commentaire:
Enregistrer un commentaire