A lire sur: Tenstep
Estimating is one of the most critical aspects of project
management. A
project management methodology will describe how to estimate. When estimating duration,
you must start off with an estimate of effort hours. Duration is a
factor of the effort hours and the resources to apply. Without an idea
of the effort hours, you cannot accurately estimate duration.
One of the key factors in converting effort hours into
duration is to define how many productive hours of work you can expect
in a typical workday. For example, if you have an activity that you
estimate will take forty effort hours; it is unlikely that it can be
completed in five eight-hour calendar days. No one is 100% productive.
Without taking this into account, it is likely that you will hit your
estimates for effort hours, but you will exceed your duration estimates.
You need a "reality factor" to convert the estimated effort hours to
estimated duration.
A productivity factor takes into account the amount of
time a typical person will actually work in a day. This productivity
factor takes into account things like social interaction during the day,
going to the bathroom and traveling to meetings. It also takes into
account people that need a little time to get going in the morning, as
well as people that start to fade in the late afternoon. You could try
to come up with the number of productive hours per day for each person
on the team, but it would be very tedious, if not impossible. A
generally accepted rule-of-thumb for average productive hours per day is
6.5, based on an eight-hour day. This is an 80% productivity factor.
When you have contract resources, you should also take a
productivity factor into account. Even though these resources are
contractors, they will still experience many of the factors that lead to
a less than 100% productivity factor. For instance, they are still going
to socialize a little and they still need to go to the bathroom.
However, you do not expect that contract people will have the same level
of non-productive time as employees. A good rule of thumb for a contract
resource is 7 to 7.25 productive hours per day. This factor recognizes
that the contract resources are not robots and they will not be 100%
productive every day. Of course, you still need to pay them for eight
hours per day. However, for the purpose of your schedule, you should
factor in the productivity factor as well.
Let’s look at an example. Let’s say you have an activity
that is estimated to take 80 hours of effort. If an employee is applied
full time, it may take him or her a little over twelve days (80 / 6.5
productive hours per day) to complete the work. If a contract resource
is allocated full time to this same activity, the activity duration
would be eleven days (80 / 7.25 productive hours per day).
Aucun commentaire:
Enregistrer un commentaire