Traceability refers to the ability to trace, or track,
requirements throughout the lifecycle and into the final solution.
Tracking requirements through the project ensures that all requirements
are built into the design, all requirements are built into the
solution, all requirements are tested and all requirements are
implemented in the final solution. This is part of a
structured lifecycle process.
Use a Traceability Matrix
The easiest way to create a link between your
requirements and other development elements is by developing a Traceability Matrix. You could just
number the requirements as "1", "2", "3", etc. However, you might want
to build more sophistication into the numbering scheme. For example, you
could give the requirements smarter names such as "TAB-001", "TAB-002", "DIS-001", "DIS-002",
etc.
Tracking requirements can be done in a couple simple ways. One way, probably the simplest,
is to just validate that each requirement is accounted for in each
project phase. For instance, something like the following table might
do.
Requirement
|
Design
|
Construct
|
Test
|
TAB-001
|
X
|
X
|
X
|
TAB-002
|
X
|
X
|
|
TAB-003
|
X
|
X
|
|
The "X" in each box validates that each particular
requirement was accounted for in each phase.
A more sophisticated example is shown below. In this
case, the requirements are tracked through each project phase and
the individual components are also identified.
Requirement
|
Design Element
|
Construct Component
|
Test Case
|
TAB-001
|
D-APR607P
|
C-APR607P
|
T-004-01
|
TAB-002
|
D-ARX607P
|
C-ARX607P
|
T-004-09, T-004-15
|
TAB-003
|
D-APC103D
D-APC103E |
C-APC103D
C-APC103E |
T-004-22
|
This tracking requires the team to keep more details as
the requirements are proceeding through the lifecycle. However, it may
be helpful to understand the details of the
initial requirement, the design element, the component that contains the
code for the requirement and the particular test case that ensured that
the requirement worked correctly.
The key thing to remember about traceability is that it
must be enforced throughout the lifecycle or else it doers not work. If
the team assigns tracking numbers to the requirements, but the
requirements are not tracked in subsequent phases, the whole
tracking scheme will break down.