A lire sur: Tenstep
    Business is always changing and the project 
    solutions that are built must reflect this change as well. You do not want to deliver a 
    solution that does not meet the business needs. That would not make 
    sense. Freezing
    change requests is 
    simply a technique to bring closure to the project. 
    The scope change freeze is an agreement with the sponsor to raise the 
    threshold for approving scope change requests. During the freeze, for instance, 
    it may be that all change requests need to be approved by the sponsor 
    personally. If the sponsor understands the benefit of the change 
    request, as well as the cost and impact to the project, she may still 
    approve the request. However, even important 
    changes may not get approved during the freeze. What may happen instead 
    is that the change will be prioritized high as part of an enhancement 
    request after the solution goes live.  
    
    How About Errors and Defects?
    You may wonder whether you can still fix errors during a 
    freeze. Remember that the freeze is on scope change requests. Of course, if you find problems or errors in the 
    solution, they can be corrected. For example, let's say you are building 
    an IT system. It is possible that when you gathered requirements you misinterpreted a 
    customer need, and that requires a change. This is not a change to the requirements, but the correcting of 
    an interpretation error. This may be allowed. Similarly, during stress testing, you 
    may find that your hardware is not powerful enough to take the load. 
    This may require changes to the system configuration, or a change in how 
    the transactions are processed. Again, this may be required under the 
    freeze. 
    Hopefully your client is not adding new business 
    requirements at the end of the project. These late changes may require 
    substantial updates to the requirements, design and the solution itself. 
    This not only requires more work. It requires the team to refocus in 
    areas that they thought were already complete. Toward the end of the 
    project the team just wants to be finished. Introducing change at this 
    late stage can lead to sloppiness and in some cases to poor morale. This is very disruptive.
    When you receive change requests toward the end of the 
    project it is better to acknowledge the changes, but put them on hold. 
    After the original project is finished, this work can be added to a 
    punch list, or a short second phase to complete separately. 
    
      
      
            
            
                  
      
            
    
      
      
            
            
                  
      
            
   
    
      
            
            
                  
      
            
            
      
      
            
            
                  
      
            
    
    
    
    
    The important points about a requirements freeze is that 
    you are recognizing that continued change requests will jeopardize your 
    ability to deliver within your budget and deadline. You gain an 
    agreement with your sponsor to allow the team to focus on a completing 
    the project as-is. 
    Critical change requests are still allowed, while less critical changes 
    are deferred until after implementation. 
 
I really appreciate information shared above. It’s of great help. If someone want to learn Online (Virtual) instructor lead live training in SIX SIGMA , kindly contact us http://www.maxmunus.com/contact
RépondreSupprimerMaxMunus Offer World Class Virtual Instructor led training on SIX SIGMA . We have industry expert trainer. We provide Training Material and Software Support. MaxMunus has successfully conducted 100000+ trainings in India, USA, UK, Australlia, Switzerland, Qatar, Saudi Arabia, Bangladesh, Bahrain and UAE etc.
For Demo Contact us.
Saurabh Srivastava
MaxMunus
E-mail: saurabh@maxmunus.com
Skype id: saurabhmaxmunus
Ph:+91 8553576305 / 080 - 41103383
http://www.maxmunus.com/