A lire sur: tenstep
When you
create a schedule you
generally don’t know enough to enter all of the detailed
activities the first time though. Instead, you identify large
chunks of work first, and then break the larger chunks into
smaller pieces. These smaller pieces are, in turn, broken down
into still smaller and more discrete activities. This technique
is referred to as creating a Work Breakdown Structure (WBS).
A question people ask is how small the activities
should be before they do not need to be broken down further.
This is referred to as your “estimating threshold”. Work can be
broken down into smaller activities than the estimating
threshold, but normally no work would be left at a higher level.
The threshold can be different based on the size of your project
and how well the work is understood.
You can use the following criteria as a guide. For a typical
large project (say 5000 effort hours or more) the activities
should be no longer than two weeks. Medium and small projects (say 1000 effort hours
or less)
should have activities no larger than one week. Remember that this threshold
is an upper limit. You can break the activities down further if
you want.
Assigning work that is smaller than your threshold allows the
work to be more manageable. Think about it. When you assign work
to a team member you don’t know for sure how he is progressing
until the due date (or the completion date if it comes first).
(Yes, you can track progress if the work proceeds linearly -
like painting a wall. But many of us work in the knowledge
business (IT, Sales, Finance) and it is not easy to know exactly
how the work is progressing.)
Let's look at an example. If you assign a team member work that
is due in four weeks, you are not going to know for sure whether
the work is on time until the four-week deadline. The worker may
tell you things are on track, but you don't really know for sure
until the due date. If the work is
completed you will know you are on track. If the work is late
you will know it then as well. However, four weeks (or longer)
is too long to wait to know if the work is on track. A better
approach is to break the four-week activity into four one-week
activities. Then you will know after the first week if the work
is on time or not.
If at all possible you want to try to have schedule work
completed within two weeks. If you give someone work that takes
four weeks or longer there is just too much time before you
really know if things are on-track or not. It is much better for
you if you can keep the schedule feedback loop to no more than
two weeks.
Aucun commentaire:
Enregistrer un commentaire