A lire sur: Tenstep
There are many ways to
build and manage a schedule. Here we are discussing Earned Value
Management. Let's recap where we ended last week.
Today's Date is March 31
|
Completed Activity
|
A
|
B
|
C
|
D
|
Remaining Work
|
|
Target Date
|
March 10
|
March 15
|
March 31
|
April 5
|
July 31
|
|
Budgeted Cost
|
20
|
10
|
15
|
5
|
500
|
|
Actual Cost
|
20
|
5
|
20
|
10
|
?
|
Let's say that as of March 31 you have
actually completed activity A, B, C and D. Let's calculate AC, PV and EV.
-
AC is the actual cost of the work completed. This is 55 (20 + 5 + 20 + 10).
-
PV is the budgeted cost of the work planned to be completed. This is 45 (20 + 10 + 15). Note that Activity D is not counted since it was not planned to be completed as of March 31.
-
EV is the budgeted cost of the work completed. This is 50 (20 + 10 + 15 + 5).
Now let's put these fundamental metrics
together in ways that provide value about the current status of schedule
and budget.
Schedule Variance (SV)
The Schedule Variance (SV) tells you
whether you are ahead of schedule or behind schedule, and is
calculated
as EV - PV. In our example above, the EV is 50 (20 + 10 + 15 + 5)
and
the PV is 45 (20 + 10 + 15). Note that the difference is activity D.
Since this activity is completed, it is included in the EV. However,
since it was not scheduled to be completed by March 31, it
is not included in the PV.
The Schedule Variance is 5 (50 - 45). If
the result is positive, it means that you have performed more work than
what was initially scheduled at this point. You are probably ahead of
schedule. Likewise, if the SV is negative, the project is probably
behind schedule.
Cost Variance (CV)
The Cost Variance gives you a sense for how
you are doing against the budget, and is calculated as EV - AC. In
our example above, the EV is 50. The AC is 55. This means that the
budget for the work completed was 50 but it actually cost 55 to complete
the work. Therefore, the Cost Variance is -5 (50 - 55). If the Cost
Variance is positive, it means that the budgeted cost to perform the
work was more than what was actually spent for the same amount of work.
This means that you are fine from a budget perspective. If the CV is
negative, you may be overbudget at this point.
Schedule Performance Index (SPI)
This is a ratio calculated by taking the EV
/ PV. This shows the relationship between the budgeted cost of the work
that was actually performed and the cost of the work that was scheduled
to be completed at this same time. It gives the run rate for the
project. If the calculation is greater that 1.0, the project is ahead of
schedule. In the example above, the SPI is equal to (50 / 45) or 1.11.
This implies that your team has completed approximately 11% more work
than what was scheduled. If that trend continues, you will end up taking
11% less time to complete the project than what was scheduled. That is a
good thing.
Cost Performance Index (CPI)
This is the ratio of taking the EV / AC.
This shows the relationship between the Earned Value and the actual cost
of the work that was performed. It gives the burn rate for the project.
If the calculation is less than 1.0, the project is overbudget. In our
example, the CPI is (50 / 55) or .91. A CPI of .91 means that for every
$91 of budgeted expenses, your project is spending $100 to get the same
work done. If that trend continues, you will end up overbudget when the
project is completed.
Budget at Completion (BAC)
This calculation can be in terms of dollars
or hours. It is the Actual Cost (AC) plus the budgeted cost of the
remaining work. If the Cost Performance Index (CPI) is not 1.0, it means
that you are spending at a different rate than your plan, and this needs
to be factored in as well. So, the better formula for the Budget at
Completion (BAC) is the AC + (Budgeted Cost of Work Remaining / CPI). In
other words, if you are running 10% overbudget to get your work done so
far, there is no reason to believe the remaining work will not also take
10% more to complete, and your final budget at completion would be 10%
over as well.
In our example above, the AC is 55 and the
Budgeted Cost of Work Remaining is 500. The estimated budget at
completion would be 55 + (500 / .91) or approximately 604.5. Since our
total budget is 550, this shows that you will be approximately 10%
overbudget.
Clicker here to view templates to
build a schedule and budget and to
manage a schedule and budget.
Aucun commentaire:
Enregistrer un commentaire